M1 Possession Planning Board

52-week rolling horizon. Drag backlog tasks onto a night window — the incompatibility matrix, Safe Approach Distances, cumulative EPL noise and event blackouts are evaluated before the task is accepted.

Tasks stacked
25
115 in backlog
Windows in use
21
107 h total track closure
Weekend windows
1
Weekend closure still in the plan
Constraint breaches
4
Windows with at least one hard failure
Horizon
T-52
Week 1 of 52
T-12 FinalTue, 18 Aug · 01:0006:007.219.8 km · UPNCA-02LOCKED
47 / 51 dB71% wrench timeClash-free

T-2 · post-lockdown change would attract 625 delay-minutes — open the window to request executive override.

T-12 FinalWed, 19 Aug · 01:0006:0043.048.4 km · DOWNNCA-07LOCKED
48 / 50 dB86% wrench timeClash-free

T-2 · post-lockdown change would attract 625 delay-minutes — open the window to request executive override.

T-12 FinalThu, 20 Aug · 01:0006:0053.558.2 km · UPNCA-08LOCKED
34 / 47 dB57% wrench timeClash-free

T-2 · post-lockdown change would attract 625 delay-minutes — open the window to request executive override.

T-12 FinalFri, 21 Aug · 01:0006:0015.327.9 km · DOWNNCA-03LOCKED
16 / 46 dB95% wrench timeClash-free

T-2 · post-lockdown change would attract 625 delay-minutes — open the window to request executive override.